Xiamen ranked first in Fujian in the accomplishment rate of key projects in progress from January to July

From January to July, 50.89 billion yuan investment was completed in Xiamen, 13.04 billion yuan more than the planned investment of 37.85 billion yuan on 111 provincial key projects. It marks that 79.8% of the annual planned investment has been completed, 21.5 percentage points more than the ordered progress. The investment completion rate ranked first for 3 consecutive months in the province. The paid-in investment of provincial key industrial projects amounted to 21.68 billion yuan, 5.02 billion yuan higher than planned for the same period. The paid-in investment of provincial key infrastructure projects amounted to 25.14 billion yuan, 7.4 billion yuan higher than planned for the same period. The paid-in investment of provincial key social projects amounted to 4.07 billion yuan, 0.63 billion yuan higher than planned for the same period.